The short life of Lisbon Valley
by Jodi Peterson
August 1995 After four years of
collecting environmental data, Summo USA Corp. applies to the
Bureau of Land Management for a permit to mine copper in Lisbon
Valley, roughly 40 miles southeast of Moab.
March 1997 The Moab BLM office approves the
mine, but enviros appeal. June 1998 The Interior Board of Land
Appeals rules against the appeal. By March 1999, Summo obtains the
required state and federal permits - then copper prices plummet,
and it can't find financing.
May 2002
Summo, now Constellation Copper, gets financing from a South
African bank. November 2004 Construction begins.
October 2005 Construction delays cause
Constellation to drop its copper production goal for 2006 from 48
million pounds to 43.5 million pounds. Workers start mining and
crushing ore, then leaching it with sulfuric acid.
April 2006 Produc-tion begins; the copper-laden
leach solution is processed to extract pure copper, and the company
turns out 804,000 pounds of the metal.
Summer/Fall 2006 To boost production,
Constellation tweaks processes. Company officials predict that in
December, the operation will produce 4.5 million pounds of copper.
Only 1.9 million pounds are produced. The total for 2006 comes to
less than 20 million pounds.
April
2007 Monthly production hits its high point - 2.2 million
pounds.
November 2007 Constellation
officials announce an end to ore mining and crushing operations,
citing expensive ongoing problems. Total copper production for the
year is about 19.7 million pounds. Over the next two years, workers
will finish processing the already-stockpiled ore; then the mine
will close down completely.
January 2008 101 Lisbon Valley employees lose their jobs; mine staffing drops to 58.